Gravity Look Ahead – Q2 2026

April – June

2026 continues to be the year when delivery can be seen in action. The progress on Agratas Building One moves at pace with the steel frame complete and installation of the cladding well underway. Agratas release regular footage of the construction site and updates can be seen here.

Similarly, our partners at National Grid Electricity Transmission (NGET) are making strong progress on the delivery of the new energy infrastructure, a vital component of the Gravity project.

As Building One continues to take shape, Agratas and their delivery partners Sir Robert McAlpine (SRM) have installed new temporary offices and welfare facilities to provide a better working environment for the new employees working on the project. It is anticipated that the number of people working on the site will reach a peak during the course of this year and Agratas are working hard to ensure that the site is as welcoming as possible for its team, whilst causing the minimum impact for local residents.

Gravity Site works

  • The Village Enhancement Scheme (VES) is on track to commence this Spring, works are expected to take six months, with the path set to open to the public later this year.
  • Construction on the new 37 Club, located in the in South West corner of the site is set to commence in the summer.
  • The steel frame of Agratas Building One has been completed and they have moved onto the roof and wall cladding installation. Work on Phase One of the Ring Road is still envisaged to begin soon, subject to compliance approval from Somerset Council. Meanwhile Agratas have launched a recruitment Register Your Interest campaign and held a series of public and school visits to the site in late March – thanks to all who attended.
  • National Grid continue their activities on site to prepare for the main constriction phase. The temporary welfare compound provides access for their workers and visitors to the site. NGET has written to nearby residents ahead of upcoming piling works starting on 8th April and taking place for approximately one week. The piling works may generate some noise and dust which will be closely monitored. Subject to the outcome of the Local Development Order Compliance Process administered by Somerset Council, NGET hope to commence main construction of the Woolavington substation later this year. Once in construction the substation will take approximately three years to complete.

Other matters

  • The respective teams will continue to respond to enquiries – see contact details below

Contacts

Gravity Look Ahead – Q1 2026

January – March

2026 will see delivery partners continue to build on the momentum established in 2025. Agratas and National Grid Electricity Transmission (NGET) will advance their respective elements of the project, marking significant milestones in the development.

Agratas will continue with the construction of Building One while installing new temporary offices to provide enhanced workspace and welfare facilities for its expanding team. This infrastructure investment will support the growing workforce as construction activity intensifies.

Gravity is preparing to deliver two important community-focused initiatives: the Village Enhancement Scheme (VES), which will connect Puriton and Woolavington via a dedicated pedestrian and cycling path, and ‘The 37’, a new facility designed to replace the outgoing 37 Club.

Gravity Site works

  • Physical works to deliver the Village Enhancement Scheme (VES) will commence in Spring, works are expected to take six months, with the path set to open to the public in the autumn.
  • Construction on the new 37 Club, located in the in South West corner of the site is due to commence in the Spring.
  • The steel frame of Agratas Building One is largely complete with cladding for the walls and roof underway soon. Concrete work to create the floor of the building will start in April. Steel work continues for the ancillary buildings that will support manufacturing in Building One, including the waste facility, storage and goods in/out. Work on Phase One of the Ring Road is also due to begin soon, subject to compliance approval from Somerset Council.
  • NGET are continuing to undertake several activities on site, under their early works programme. They have established a temporary construction compound, including welfare units and parking for workers. Subject to the outcome of the Local Development Order Compliance Process administered by Somerset Council, NGET aim to commence main construction of the Woolavington substation later this year. NGET will share updates with local residents ahead of starting the main construction phase. Once in construction the substation will take approximately three years to complete.

Other matters

  • The respective teams will continue to respond to enquiries – see contact details below

Contacts

Gravity Look Ahead – Q4 2025

Gravity Look Ahead - Q4 2025

October – December

As we move into Autumn, activity across the delivery partners on site will continue at pace. Following the installation of necessary utilities for Gravity and Agratas, Woolavington Road reopened to the public on time in late August. We would like to thank the local community for their patience.

Since Agratas commenced development under the LDO in the summer, over 4,000 tonnes of steel have been erected, and Building One is taking shape. See Agratas’ latest construction update video on Building One here.

Balfour Beatty are undertaking early site setup works associated with the National Grid Electricity Transmission (NGET) substation. This includes the setup of a temporary construction compound adjacent to Woolavington Road. The substation provides a vital grid connection point for Agratas and the wider Gravity development. The associated Local Development Order compliance submission for the Woolavington substation is now expected to be submitted to Somerset Council in Q4.

Gravity Site works

  • Onsite works to divert the existing mains gas supply are progressing and will be completed imminently.
  • Stantec on behalf of This is Gravity and Agratas are coordinating the installation of five air quality sensors, these are due to be installed on Thursday 30th October. This programme forms part of the approved Local Development Order for the Gravity site. Further details can be found here.
  • This is Gravity are expecting to initiate the works to deliver the Village Enhancement Scheme (VES) in Q4. Physical works will commence in Q1, 2026. Completion of these works will see Puriton and Woolavington connected by a pedestrian/cycle path, as well as traffic calming measures introduced in both villages.
  • Agratas has now received planning consent for the amendments to Building One. The application for Phase One of the Ring Road has been submitted to the council, with work expected to start early in 2026. Groundwork continues across the site, including on the platform for the new NGET substation.
  • Since the beginning of September, Balfour Beatty have been undertaking early works, establishing a temporary construction compound and welfare area off Woolavington Road. From late October, NGET will be carrying out further early works, laying foundations for the gantries situated underneath the existing overhead lines. NGET’s main construction works are currently programmed to start in the New Year, subject to the Local Development Order Compliance Process.

Other matters

  • The respective teams will continue to respond to enquiries – see contact details below

Contacts

This notice can be downloaded as a PDF here.

Gravity Look Ahead – Q3 2025

July – September

As we move into summer, activity across Gravity’s delivery partners has ramped up. A key milestone was reached in late June, when construction officially commenced under the Local Development Order (LDO), marked by the first steel deliveries for Agratas’ Building One structure.


National Grid Electricity Transmission (NGET) has progressed its early works, completing a temporary compound and platform base that will enable the delivery of its substation. Meanwhile, delivery partners are working towards a coordinated dust suppression strategy in anticipation of continued dry weather.


LDO compliance submissions have been submitted by This is Gravity Ltd for the new leisure facilities that will replace the 37 Club, and by Agratas for the revised Building One. The next LDO compliance submissions are expected for NGET’s substation and the first phase of the internal ring road.

Gravity Site works

  • Works to connect the site to essential utilities are progressing on schedule. The electricity connection work is now complete, and the next phase has started. This will be focused on the gas connection work to be carried out by Wales and West Utilities on behalf of This is Gravity. The closure of Woolavington Road is expected to continue until late August. Community questions during these phases should be directed to the Wales & West Utilities contact listed below.
  • Agratas and SRM have had extended working hours for steel related works agreed subject to a Section 61. Until December 2025 working hours will be; Monday to Friday: 07:00 – 19:00, Saturday: 07:00 – 18:00 and Sunday: 10:00 – 17:00. Click here to read about the measures to be taken to mitigate the impacts of the extended working hours. Community queries on this should be directed to the construction team via the SRM contact details listed below.
  • The formal completion and adoption of Enterprise Way by Somerset Council is under discussion between Gravity, Alun Griffiths and Somerset Council. Subject to agreement to carry-over remaining defects to the defect liability period, the completion certificate can be issued. Following the re-opining of Woolavington Road, works will then start on theVillage Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.

Other matters

  • Upcoming LDO compliance submissions include the NGET substation and the first phase of the internal ring road.
  • The respective teams will continue to support and respond to enquiries – contact details are found below.

Contacts

  • Gravity: info@thisisgravity.co.uk / 0207 160 0006
  • Agratas: communityuk@agratas.com
  • NGET: woolavington@nationalgrid.com / 0800 073 1047
  • SRM: agratas.community@srm.com / 0333 566 1122
  • Wales & West Utilities: Peter Withecombe – 07779878887

View and download the PDF version here.

Gravity Look Ahead – Q2 2025

April – June

The new Enterprise Way site access opened during Q1, while the former site entrance will still be used as needed. In early April, community consultation events were held regarding the proposed ring road, amendments to Building One and the NGET substation.

To connect the site to essential utilities, sections of Woolavington Road (between Enterprise Way and Woolavington Village) will be closed in phases, starting April 14th and lasting up to five months. Somerset Council will share finalised details on which parts will be closed when. All residents and businesses on Woolavington Road will have access to their properties throughout the closures.
Click here for more information.

Gravity Site works

  • TIG contractors are monitoring the landscaping on the link road (Enterprise Way) and replacing, as necessary until completion is formally signed off.
  • Substructures for the first phase of the build are now complete, and a subcontractor has been selected for the structural steel with initial order placed, targeting June 2025 commencement on site.
  • The formal completion and adoption of Enterprise Way by Somerset Council is expected after snagging has been completed by the contractor. Works will then start on the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
  • National Grid Electricity Transmission (NGET) was also present at the April community consultation sessions to discuss plans for their proposed substation, which will power the Agratas facility and wider parts of the Gravity Smart Campus.
  • Site preparation and early works will continue, including material import and management.
  • Work to recycle site material will continue.

Other matters

  • Formal governance arrangements required under the LDO with the Council and other partners are now in place.
  • Enquiries- the respective teams will continue to support and respond to enquiries.

Contact Gravity

Contact Agratas

Contact Sir Robert McAlpine (SRM)

View and download the PDF version here.

Gravity Look Ahead – Q1 2025

January – March

Following Somerset Council’s approval of the site’s first major building through the Local Development Order (LDO) compliance process, on-site activity will increase. 2025 will see the commencement of construction of the first battery cell manufacturing facility ‘Building One’.

This is Gravity (TIG) continues to support the delivery of the battery cell manufacturing facility and the development of site infrastructure and wider campus amenities. TIG is also in discussions with the Council as to the development of the balance of the site.

Gravity Site works

  • TIG contractors are monitoring the landscaping on the link road (Enterprise Way) and replacing, as necessary until completion is formally singed off.
  • Ground works and foundation construction (piling) continues for Agratas’s first building on site, view their videos here.
  • The formal completion and adoption of Enterprise Way by Somerset Council is expected after snagging has been completed by the contractor. Works will then start on the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
  • National Grid will by early February be communicating with local residents to introduce its role in the Gravity development and share plans to build a new substation on the Gravity site. They are a key enabler to provide the necessary infrastructure for the whole of Gravity.
  • Site preparation and early works will continue, including material import and management.
  • Work to recycle site material will continue.

Other matters

  • Formal governance arrangements required under the LDO with the Council and other partners are now in place
  • Enquiries- the respective teams will continue to support and respond to enquiries.

Contact Gravity

Contact Agratas

Contact Sir Robert McAlpine (SRM)

View and download PDF here.

Gravity Look Ahead – Q4 2024

October – December

As we move into Autumn, activity at the Gravity site will continue to accelerate. This is Gravity (TIG) continues to support the delivery of the advanced battery manufacturing facility, site infrastructure and wider campus amenities.

Summer saw Sir Robert McAlpine (SRM) appointed by Agratas for the construction of the first major building on site – Building One.

Gravity Site works

  • Site preparation for Agratas will continue, including material import and management.
  • Work to recycle site material will continue.
  • TIG contractors will be monitoring the new landscaping on the link road (Enterprise Way) and replacing, as necessary, to ensure completion as soon as possible.
  • Ground works and foundation construction (piling) continues for Agratas’s first building on site.
  • Work is well underway to open the new main entrance to site directly from the Woolavington Road roundabout, reducing the proportion of construction vehicles utilising Woolavington Road.
  • Environmental monitoring equipment to report on noise and air conditions has been installed. Data from this equipment will be reported to the Council governance groups, once fully established.
  • The formal completion and adoption of Enterprise Way by Somerset Council is expected after snagging has been completed by the contractor. Works will then start on the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
  • Following meetings with local stakeholders, National Grid will soon be communicating with local residents to introduce plans to build a new substation on the Gravity site. They are a key enabler to provide the necessary infrastructure for the whole of Gravity

Other matters

  • Gravity welcomes David Oakhill as its Director of Planning and Economic Development.
  • Ground investigations will continue throughout the autumn months.
  • Formal governance arrangements required under the LDO with the Council and other partners are now in place.
  • Enquiries – the respective teams will continue to support and respond to enquiries.

Contact Gravity

Contact Agratas

Download PDF here.

Look Ahead – Q3 2024

July – September

As we move into summer the site will maintain high levels of activity. This is Gravity (TIG) continues to support Agratas, and other leading partners in the delivery of the advanced battery manufacturing facility, site infrastructure and wider campus amenities.

Site works

  • Site preparation and early works will continue including material import and management.
  • The work to recycle concrete from the site and crush it for re-use will continue.
  • Work with Somerset Council (SC) and other stakeholders is ongoing to establish and operate formal project governance meetings as well as community and business groups, we look forward to sharing more information as these develop.
  • TIG contractors will monitor the new landscaping on the link road (Enterprise Way) and replace as necessary.
  • Environmental monitoring equipment to report on noise and air conditions has been installed, data from this equipment will be reported to the Council as appropriate and governance groups when these are established.
  • The formal completion and adoption of Enterprise Way by Somerset Council is expected after the contractor has completed the snagging, then triggering the s106 timeline for delivery of the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Puriton and Woolavington and traffic calming measures. TIG are well prepared for this with the scheme designed in readiness, to avoid any delays to implementation.
  • National Grid will be contacting local stakeholders to introduce their role in the delivery of the project and offering initial briefingsThey are a key enabler to provide the necessary infrastructure for the whole of Gravity.

Other matters

  • Consultant site visits and ground investigations will continue across the summer months.
  • Enquiries – the respective teams will continue to support and respond to enquiries.

Contact Gravity

Contact Agratas

Look Ahead – Q2 2024

April – June

As we move into Spring, the Gravity site will become more active as we transition into delivery, the two landowners at the Gravity smart campus, This is Gravity (TIG) and Agratas will coordinate and jointly communicate where possible.

Site works

  • The work to recycle concrete from the site and crush it for re-use will continue. 
  • In line with our material management strategy the import of recycled aggregate from the Hinkley C connection resumed in March.
  • The import of aggregate to meet occupier needs as required will continue.
  • TIG contractors will be monitoring the new landscaping on the link road and replacing as necessary.
  • In preparation for the construction phase, we are installing environmental monitoring equipment to report on noise and air conditions.
  • The campus approach to reuse and recycling seeks to reduce traffic movements.
  • Consultant site visits and ground investigations will also take place. 
  • TIG archaeology investigations will take place on part of the site outside of the original ROF fence in late April/early May for about 12 weeks. 
  • Test piling for Agratas began on March 26th, it will take place for short periods throughout the day (08:00 – 18:00), Monday to Friday, measures to keep noise to a minimum and to limit excess dust on site by using water tankers if conditions are dry. Test piling will last for approximately three weeks.
  • Piling will commence once the test piling has been completed with the final piles designed. Further information on this will be provided by Agratas.

Other matters

  • Agratas will be hosting a series of public drop-in events between April 27 and May 2. Event leaflets have been shared, updates communicated via Agratas’ WhatsApp channel and information listed on Puriton and Woolavington Parish Council websites. Click here for further information about the Bridgwater event on April 30.
  • Multiple LDO compliance submissions will be progressed in the coming months for various uses across the site.
  • TIG will continue with its work to replace the leisure facilities currently hosted by the 37 Club. Plans for the new facility are on display at the current 37 Club.
  • Submissions to Somerset Council and other regulators on planning and technical matters will continue as appropriate.

Contact

Look Ahead – Q1 2024

As we emerge from the Winter months work at the Gravity site will ramp up and the community will see more activity. This is a welcome sign as the site moves into implementation.

There are now two landowners at the Gravity smart campus and works will be coordinated and activity communicated jointly where possible. This is Gravity (TIG) who secured the Local Development Order remain as one landowner. Other occupiers will be announced in due course.

Planned Site Works

  • The work to recycle concrete from the site and crush it for re-use will continue.
  • Import of recycled aggregate from the Hinkley C connection project will also resume (weather dependent) towards the end of March.
  • Import of aggregate to meet occupier needs as required.
  • TIG contractors will be monitoring the new landscaping on the link road and replacing as necessary.
  • Tree works on site will take place before bird nesting season to prepare for implementation.
  • The campus approach to re-use and recycling seeks to reduce traffic movements.
  • Consultant site visits, ground investigations will also take place.
  • TIG Archaeology investigations will take place on part of the site outside of the original ROF fence, late March / early April for about 12 weeks.

Other matters

  • TIG will continue to be represented locally by Claire Pearce as Director of Planning and Economic Development, Paul Lowndes as Programme Director on site, and Rob Stevens providing communications support. We welcome Stuart Houlet to the Gravity family as Head of Planning for TIG.
  • TIG will continue with its work to replace the leisure facilities currently hosted by the 37 Club.
  • Submissions to Somerset Council and other regulators on planning and technical matters will continue as appropriate.

View as PDF

View previous look-ahead documents.

We're sorry to see you go!



Company Name

Text about the company etc…

www.linktowebsite.com