Join representatives from This is Gravity Ltd, Gleeds, and Stantec as they present details of the Village Enhancement Scheme (VES), explain the planned works, and answer any questions.
As we move into Autumn, activity across the delivery partners on site will continue at pace. Following the installation of necessary utilities for Gravity and Agratas, Woolavington Road reopened to the public on time in late August. We would like to thank the local community for their patience.
Since Agratas commenced development under the LDO in the summer, over 4,000 tonnes of steel have been erected, and Building One is taking shape. See Agratas’ latest construction update video on Building One here.
Balfour Beatty are undertaking early site setup works associated with the National Grid Electricity Transmission (NGET) substation. This includes the setup of a temporary construction compound adjacent to Woolavington Road. The substation provides a vital grid connection point for Agratas and the wider Gravity development. The associated Local Development Order compliance submission for the Woolavington substation is now expected to be submitted to Somerset Council in Q4.
Gravity Site works
Onsite works to divert the existing mains gas supply are progressing and will be completed imminently.
Stantec on behalf of This is Gravity and Agratas are coordinating the installation of five air quality sensors, these are due to be installed on Thursday 30th October. This programme forms part of the approved Local Development Order for the Gravity site. Further details can be found here.
This is Gravity are expecting to initiate the works to deliver the Village Enhancement Scheme (VES) in Q4. Physical works will commence in Q1, 2026. Completion of these works will see Puriton and Woolavington connected by a pedestrian/cycle path, as well as traffic calming measures introduced in both villages.
Agratas has now received planning consent for the amendments to Building One. The application for Phase One of the Ring Road has been submitted to the council, with work expected to start early in 2026. Groundwork continues across the site, including on the platform for the new NGET substation.
Since the beginning of September, Balfour Beatty have been undertaking early works, establishing a temporary construction compound and welfare area off Woolavington Road. From late October, NGET will be carrying out further early works, laying foundations for the gantries situated underneath the existing overhead lines. NGET’s main construction works are currently programmed to start in the New Year, subject to the Local Development Order Compliance Process.
Other matters
The respective teams will continue to respond to enquiries – see contact details below
Stantec on behalf of This is Gravity and Agratas are coordinating the installation of five air quality sensors. Specifically, three sensors will be installed in Puriton and two in Woolavington. This programme forms part of the approved Local Development Order for the Gravity site.
The monitoring will take place for a number of years as the Gravity development is built out and occupied however, there are no air quality related issues expected to arise from the development.
The air quality sensors will be mounted to existing street lighting columns with two of them being accompanied by a wind speed and direction sensor. The sensors are being mounted to the street-lighting columns by Stantec and the electrical work on the street-lighting columns will be being completed by Volkers who are Somerset Councils lighting contractor.
The Air Quality sensors will be installed on Thursday 30th October
As we move into summer, activity across Gravity’s delivery partners has ramped up. A key milestone was reached in late June, when construction officially commenced under the Local Development Order (LDO), marked by the first steel deliveries for Agratas’ Building One structure.
National Grid Electricity Transmission (NGET) has progressed its early works, completing a temporary compound and platform base that will enable the delivery of its substation. Meanwhile, delivery partners are working towards a coordinated dust suppression strategy in anticipation of continued dry weather.
LDO compliance submissions have been submitted by This is Gravity Ltd for the new leisure facilities that will replace the 37 Club, and by Agratas for the revised Building One. The next LDO compliance submissions are expected for NGET’s substation and the first phase of the internal ring road.
Gravity Site works
Works to connect the site to essential utilities are progressing on schedule. The electricity connection work is now complete, and the next phase has started. This will be focused on the gas connection work to be carried out by Wales and West Utilities on behalf of This is Gravity. The closure of Woolavington Road is expected to continue until late August. Community questions during these phases should be directed to the Wales & West Utilities contact listed below.
Agratas and SRM have had extended working hours for steel related works agreed subject to a Section 61. Until December 2025 working hours will be; Monday to Friday: 07:00 – 19:00, Saturday: 07:00 – 18:00 and Sunday: 10:00 – 17:00. Click here to read about the measures to be taken to mitigate the impacts of the extended working hours. Community queries on this should be directed to the construction team via the SRM contact details listed below.
The formal completion and adoption of Enterprise Way by Somerset Council is under discussion between Gravity, Alun Griffiths and Somerset Council. Subject to agreement to carry-over remaining defects to the defect liability period, the completion certificate can be issued. Following the re-opining of Woolavington Road, works will then start on theVillage Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
Other matters
Upcoming LDO compliance submissions include the NGET substation and the first phase of the internal ring road.
The respective teams will continue to support and respond to enquiries – contact details are found below.
A letter has been distributed to Woolavington Road residents to provide an update on the phased closures of Woolavington Road that started in April.
The electricity connection work is now complete and the next phase will begin soon.
This will be focused on the gas connection work to be carried out by Wales and West Utilities on behalf of This is Gravity.
If you have questions during these phases please contact Peter Withecombe at Wales & West Utilities on 07779878887.
Works Phasing and Closure dates :
Closure dates: (see map for reference)
Sections 5 & 3 – 30/06/25 to 11/07/25
Sections 4 & 2 – 14/07/25 to 25/07/25
Section 1 – 28/07/25 to 28/08/25
These closures will continue until late August. We will share updates to keep you informed of progress and the expected completion date.
Please be assured that all residents and businesses on Woolavington Road will be able to access their properties throughout these closures. Local businesses, the 37 Club and Woolavington Surgery will be open as usual.
General traffic will need to follow the diversion via Puriton Hill and Bath Road to travel between Puriton and Woolavington. A pedestrian and cycle path is being maintained through the work site – please remember that this is a shared space.
We appreciate that these necessary works will cause some disruption, and we thank you for your patience as we prepare for main construction on the Gravity and Agratas sites.
If you have any questions or concerns about this phase of the road closures please email the team via info@thisisgravity.co.uk
Representatives from Gravity attended three community consultation events hosted in Puriton and Woolavington between April 1st and April 5th.
Across the events, Agratas discussed their latest plans for ‘Building One’ and the proposed ring road. National Grid Energy Transmission (NGET) were at the consultation events presenting their plans for the proposed Woolavington substation, which will power the Agratas facility, as well as wider parts of the Gravity Smart Campus.
Agratas’ display boards were presented with the details, which you can find here.
Feedback on Agratas’ latest plans can be submitted here.
Feedback on NGET’s proposed substation can be submitted here.
The new Enterprise Way site access opened during Q1, while the former site entrance will still be used as needed. In early April, community consultation events were held regarding the proposed ring road, amendments to Building One and the NGET substation.
To connect the site to essential utilities, sections of Woolavington Road (between Enterprise Way and Woolavington Village) will be closed in phases, starting April 14th and lasting up to five months. Somerset Council will share finalised details on which parts will be closed when. All residents and businesses on Woolavington Road will have access to their properties throughout the closures. Click here for more information.
Gravity Site works
TIG contractors are monitoring the landscaping on the link road (Enterprise Way) and replacing, as necessary until completion is formally signed off.
Substructures for the first phase of the build are now complete, and a subcontractor has been selected for the structural steel with initial order placed, targeting June 2025 commencement on site.
The formal completion and adoption of Enterprise Way by Somerset Council is expected after snagging has been completed by the contractor. Works will then start on the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
National Grid Electricity Transmission (NGET) was also present at the April community consultation sessions to discuss plans for their proposed substation, which will power the Agratas facility and wider parts of the Gravity Smart Campus.
Site preparation and early works will continue, including material import and management.
Work to recycle site material will continue.
Other matters
Formal governance arrangements required under the LDO with the Council and other partners are now in place.
Enquiries- the respective teams will continue to support and respond to enquiries.
As spring approaches, roadworks to extend utilities to Agratas and Gravity progress closer to the site, requiring local road closures to facilitate the work.
To connect the site to the necessary utilities, sections of Woolavington Road between Enterprise Way roundabout and Woolavington Village will be closed in phases, starting from April 14th, lasting up to five months.
Details of which sections will be closed when will be shared by Somerset Council locally when they have been finalised. All residents and businesses on Woolavington Road will be catered for and will be able to access their properties throughout these closures.
Gravity and Agratas’ contractors will be doing their best to complete the works in less than five months.
Somerset Council’s Traffic Management Team has been liaising with contractors to coordinate their work and make sure they access to the road together, instead of the road needing to be closed multiple times.
Gravity will join Agratas at the upcoming community consultation sessions planned for early April. The sessions are designed to keep residents informed and will provide an opportunity for community members to:
Review the proposed new ring road design
Explore first-phase building adaptations
Provide direct feedback on project developments
Event details:
1st April – Woolavington Village Hall – 17:00-19:00
Following Somerset Council’s approval of the site’s first major building through the Local Development Order (LDO) compliance process, on-site activity will increase. 2025 will see the commencement of construction of the first battery cell manufacturing facility ‘Building One’.
This is Gravity (TIG) continues to support the delivery of the battery cell manufacturing facility and the development of site infrastructure and wider campus amenities. TIG is also in discussions with the Council as to the development of the balance of the site.
Gravity Site works
TIG contractors are monitoring the landscaping on the link road (Enterprise Way) and replacing, as necessary until completion is formally singed off.
Ground works and foundation construction (piling) continues for Agratas’s first building on site, view their videos here.
The formal completion and adoption of Enterprise Way by Somerset Council is expected after snagging has been completed by the contractor. Works will then start on the Village Enhancement Scheme (VES), which includes a pedestrian and cycle path connecting Purtion and Woolavington and traffic calming measures.
National Grid will by early February be communicating with local residents to introduce its role in the Gravity development and share plans to build a new substation on the Gravity site. They are a key enabler to provide the necessary infrastructure for the whole of Gravity.
Site preparation and early works will continue, including material import and management.
Work to recycle site material will continue.
Other matters
Formal governance arrangements required under the LDO with the Council and other partners are now in place
Enquiries- the respective teams will continue to support and respond to enquiries.